BGP2 Procurement Opportunity
Details of the opportunity:
Steel Partitioning – Workshop Areas
Double Skin Steel Partitioning 3.000m High
Solid to 1.200m Single Glazed to 2.022m Solid above
Doors to include Vision Panels and Key Locks 6mm Clear Toughened Glass
Powder Coated white
1 – Run 30.503m to include 4 no Standard Double Doors & 6 no S/G/S panels
3 – Runs 8.000m Solid
2 – Runs 8.000m Solid to include 1 no Standard Double Door in each run
1 – Run 2.691m Solid
1 – Run 5.553m Solid to include 1 no Standard Single Door
1 – Run 1.650m Solid
Single Skin Built As Double Skin for wall lining to blockwork wall
1 – Run 32.153m Long
Strip curtain to weld bay
Ceilings
600mm x 600mm Plastic Faced Plasterboard tiles Laid into a White Tee Grid
100mm insulation pads laid over the suspended ceiling tiles
Wire Suspended from Galvanised Support Beams
Facia to exposed edges
Area 275 m2
All the above for the sum of £xxxxx.xx
Lighting and Power
Supply, deliver and install
40 No 600 x 600 LED panel lights laid in suspended ceiling grid
Emergency lighting as required
43 No double sockets, faced fixed, cables in trunking (not 3 compartment trunking)
All wired back to the existing distribution board
For the sum of £ xxxx.xx
Fire alarm – Budget Sum £ xxx.xx
Jumbo Stud Wall
Supply, deliver and install jumbo stud and plasterboard wall near the roller shutter.
Tape, joint and paint finish.
Steelwork allowed for within the wall for partial strip out if required in the future.
Double door within the wall, currently allowed for each door leaf to be 1200mm wide x 2400mm high. Size to be confirmed.
For the sum of £ xxxx.xx
Extra Over Items
Supply and install open and close vents in doors
For the sum of £ xxx.xx
All prices to be quoted excluding VAT
Please note
Lead time is approx. X weeks from order.
Terms of Payment: XXXX
What is required from all interested parties
Please register interest with p.harper@midwaymanufacturing.co.uk
If a site survey or dwg file of the unit is required, no problem, just let us know asap.
How successful candidate will be chosen
Best prices and to be specified as per above with same/similar quality of materials.
Lead time of installation is imperative and needs to be 6 weeks or under.
Working over the Christmas period is desirable.
Deadline and details of how to apply
All applications must register interest with p.harper@midwaymanufacturing.co.uk
Official quote should be submitted by the 4th December at 5pm and have the reference – Midway Scientific RFQ001